Monday - Friday 7 a.m. - 5 p.m. call (708) 403-6350
After-hour emergency, call the non-emergency police at (708) 349-4111
This project is the second phase of the Catalina improvement plan that began last year with the watermain lining. This phase will see work done on both the local watermains and storm sewers as both systems are upgraded to better meet the needs of local residents. Unlike the lining work performed in 2023, the water and sewer mains will be fully replaced. As a result, there will be greater impacts to local traffic as work is conducted in the roads, but affected residents will not need to be placed on a temporary water service system. Crews will begin mobilizing in early April, with work to begin shortly thereafter. This year’s efforts will focus on the western portion of the Catalina neighborhood while the remaining eastern portion is scheduled to be finished in 2025.
Temporary asphalt patching will be put over the affected roadways at the end of this year’s project while more extensive road resurfacing will take place during 2025 as part of the Village’s Road Improvement Program.
UPDATE (10/9/2025): Concrete curb and sidewalk restoration are largely complete, with only a few small patches remaining. Asphalt restoration began earlier this week and is expected to be substantially completed by the end of the week. Landscape work has also begun and will likely carry into next week. The new retention pond south of Kruse School is now estimated to be substantially complete by early November. We’re still targeting the end of November for full project completion.
In 2023, Public Works began a multi-year effort to restore and naturalize the Municipal Basin between Ravinia Avenue and West Avenue, also known as the Ravinia Creek Wetland. This project was broken into two phases – one phase to remove the existing invasive plant species and another to bring in native plant species to repopulate the wetland. Our contractor, Davey Resource Group, kicked off the first phase by mowing down a significant portion of the invasive phragmites reeds that dominated the wetland and then performed a controlled burn to destroy the remaining stalks.
UPDATE (4/21/25): The third controlled burn at the wetland has been completed. Now, Davey Resource Group will begin planting native seed species and working throughout the year to promote their growth. By Summer of next year the wetland should be full of new, healthier wild grasses and flowers.
During the summer of 2025 Public Works will be working with its contractor, PT Ferro Construction, to replace several hundred feet of deteriorating storm sewer pipe in the area of 144th Street and Irving Avenue. The majority of this work will take place within the parking lot of Saint Michael Church where the existing storm sewer runs through. For residents who attend Saint Michael Church, please understand that portions of the parking lot will be closed while work is ongoing, though we do not anticipate this project to interrupt any regularly scheduled church activities or events. Construction is scheduled to be completed by mid-August so as not to disrupt local school traffic.
The Village maintains fifty-five (55) playgrounds spread across sixty-six (66) park sites. According to the 2020 NRPA Agency Performance Review, which highlights characteristics of America’s local public park agencies, a community with a population range between 50,000 to 99,999 has on average one (1) playground for every 3,859 residents. With a population of roughly 60,000, the Village of Orland Park fairs substantially better, with one (1) playground for every 1,090 residents. Since 2020, the Public Works Department has renovated twenty-seven (27) Village playgrounds. The order of playground renovations has been largely based on data outlined in the 2019 Village Park Assessment. An updated Park and Pavilion Assessment was completed in 2023 and outlines the direction for current and future park improvements.
Playground renovations at Country Club Estates, Laurel Hill, Eagle Ridge III Parks were completed in 2025. Doogan and Schussler Parks will also receive playground upgrades as a part of overall park renovations later this year. Playground improvements include new playground equipment, accessibility improvements and site amenities.
For park locations, please visit Find a Park.
This fall, the Village will replace the swing bays at Helen Park, Grasslands Park, and Evergreen View Park. These parks are scheduled for new playground units in 2026; however, the decision was made to use remaining funds from 2025 to replace the swing bays at these parks this year. Because these playgrounds have a larger footprint, installing the swings this year will allow for the allocation of full funding to the playground structure, giving the residents more amenities to enjoy. Attached are images of the swing bays to be installed at each park.
There are currently sixty-one (61) pavilions located throughout the Village's Parks system. Park pavilions provide a place in the shade for residents to congregate, watch their children play or enjoy lunch. Park pavilions are typically located in close proximity to a playground.
The installation of two (2) park pavilions are scheduled to be installed in 2025 at Doogan Park (new) and Helen Park (replacement). New picnic tables will also be added to each pavilion.
For park locations, please visit Find a Park.
To notify residents of the upcoming playground and pavilion projects, the Village sends postcards to residents who live within three hundred (300) feet of the parks where projects are proposed. Postcards include general information about the projects as well as a QR Code that links to the website where more detailed information is available. A survey is posted on the Public Works website for residents to vote on their preferred playground option (A or B) and provide comments regarding the projects. An invitation is also included on the postcards to the Recreation Advisory Board (RAB) meeting where the proposed projects are publicly discussed. Finally, signs are placed at each park to notify residents of upcoming park projects and to direct them to the Public Works website. Signs announcing the temporary closure of each park will be posted during construction.
The results of resident feedback regarding 2025 Playground and Pavilion Projects will be presented at the Recreation Advisory Board (RAB) on Tuesday, February 4, 2025 at 6:00PM at the Civic Center (14750 S. Ravinia Ave). This is a public meeting and visitors will have the opportunity to comment within the guidelines of the meeting. The RAB will be making a recommendation to the Village Board of Trustees at this meeting regarding the proposed projects.
To better understand the state of the Village’s parks, the “2023 Playground and Pavilion Assessment” was completed between November, 2023 and January, 2024 by Certified Playground Safety Inspectors (CPSI) from Studio GC. In contrast to the 2019 Assessment, the 2023 Assessment focuses solely the condition of playground and pavilions. The goal of the assessment was to provide a roadmap for the next five (5) years (2024 – 2028) for playground and pavilion renovations. A copy of report can be found here:
2025 Street Asphalt Patch Locations
For a full map of all concrete flatwork, asphalt and sidewalk work, click here.
2025 Sanitary Manhole Rehabilitation Project Begins This Week
The Village of Orland Park has selected Airys Inc., with subcontractor Hoerr Construction, to perform sanitary manhole rehabilitation across the community.
To keep residents informed, Public Works staff personally delivered a letter to every home with a manhole located either in the backyard or front parkway.
Questions? Contact Nick Hedges (Airys Inc.) at 708-429-0660 or Public Works at 708-403-6350.
The Village of Orland Park has selected Sewertech LLC to clean and televise sewers in your area. The work will be starting in September 2025.
To keep residents informed, the Village will send a notice out 48 hours prior to the contractor coming.
Work on the 2024 Parkway, Park and Facility Tree Assessment has been completed. Crews from Great Lakes Urban Forestry Management (GLUFM) assessed and inventoried all public trees located in parkways and park/facility grounds, a total of 36,134 trees!
Stripping June 2025
Longer Stretches
1. Will/Cook from Route 6/Southwest Highway to 167th St. 1.9 miles 10,032ft) yellow striping in center lane. Turn lanes at both ends.
2. Westbrook Dr and Will Cook Rd yellow striping (0.4 mile 2112ft) and white lane strip and turn lane markings.
3. Starting half way from Acadia Dr going east to Old Orchard Ct and going west from 82nd Ave to right before Acadia Dr. (930ft of solid white striping both sides) and yellow striping in center lanes.
4. West Ave from 153rd St. going N to 143rd St. (1.25 miles 6600ft) Yellow striping center lane and all turn lanes.
5. Ravinia Ave from 153rd St. going N to 143rd St. (1.25 miles 6600ft) Yellow striping center lane and all turn lanes.
6. 156th St. to 94th Ave. by Lowes all the streets all crosswalks, solid yellow in center and turn lanes. (3800ft)
7. The Preserve at Marley Creek whole subdivision
Shorter Stretches
Remember it is important to call to have utility lines marked before you dig. This is a free service. Call 8-1-1 or 1-800-892-0123. Visit https://www.illinois1call.com/ for more information regarding utility line markings.
Below is a list of what color each flag represents:
Mosquito season starts during the summer months and continues through fall.
The Village relies on the South Cook County Mosquito Abatement District (SCCMAD) for administration of the Mosquito Abatement Program. SCCMAD's mission is to safeguard the health and comfort of the citizens of South Cook County through a planned program to monitor and reduce mosquitoes and other biting insects that transmit diseases or parasites from one human or animal to another, known as vectors.
PREVENTION
The most effective way to prevent mosquito borne virus infections from mosquito bites is to prevent them in the first place. Mosquitoes bite during the day and the night, use an insect repellent, wear long-sleeved shirts and pants, treat clothing and gear, and take steps to control mosquitoes indoors and outdoors.
You are first in line to be bitten by mosquitoes that breed in your own yard and garden! Mosquitoes can breed even in the tiniest amounts of water. Remove stagnant water so mosquitoes can’t breed.
Have questions regarding the program? Please contact the South Cook County Mosquito Abatement District office at (708) 333-4120 or visit them online at the Cook County Mosquito Abatement website.
Lake Lucille Agreement 03/31/1989
Letter from Erick Peck, Attorney for Palos Township Highway Department 07/29/2021
Woodland Shores Agreement 01/19/1987
Lake Lucille-Woodland Shores Information Request Final JVE 9.17.21
Woodland Shores 1 and 2 Subdivision Plat
Question 24- Stormwater Master Plan Scope of Work
Question 31- Water Rate Study Orland Park W-S-SW Model 02-29-16 Final
Question 33- Stormwater flow diagram
Question 35- Emails APWD asking Palos Township if they would do eminent domain
Question 36- Emails of data gathering
Question 21- Orland Park Rate Recommendations Memorandum 02-29-16
Question 21- Water & Sewer Rates 1991-0213
Question 21- Water & Sewer Rates 1998
Question 21- Water & Sewer Rates 2002-2006 - adjusted per Water Rate Study
Question 21- Water & Sewer Rates 2007-2012
Question 21- Water Rate Breakdown 2012-2021
Question 3- Old P 28-02 Pond Tickets
Question 3- Old P28-01 Pond Tickets
Question 3- Tyler_WoodlandShore_LakeLucille_Tickets
Question 4- Utilities Equipment List
Question 5- FY22-26 Capital Requests
Question 9- Service Area Outside VOP
Orland Park Pond Evaluation Checklist
Call (708) 403-6350 or e-mail publicworks@orlandpark.org.
Call (800) 964-8988 or Click here for more information.
Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.
Windows Media Player
Word Viewer
Excel Viewer
PowerPoint Viewer