When applying for new detached garage permits, digital plans are required as well as the following:
A dimensional floor plan showing location of service doors, windows, headers, location of electrical receptacles, etc.
Layout of rafters and direction and span of rafters or trusses
Height measurement from the peak of the garage to the average perimeter grade
Plat of survey showing the location of the new detached garage with setbacks from side and rear property lines and the location of any additional driveway work to be done
Completed zoning permit application
Completed electrical permit application
Separate driveway permit if additional driveway surface is required
Separate demolition permit if there is an existing detached garage to be removed
Grading Plan
A detailed grading plan may be required if requested by engineering after their visual on-site inspection.
Final inspection of demolition of existing garage, if applicable
Rough inspections including framing and electrical, before the drywall is installed
Pre-pour inspection for the driveway, if applicable
Final inspection of framing and electrical, upon completion of work
Please submit an inspection request. Inspection requests are not taken over the phone. Requests for inspections must be made a minimum of 24 hours in advance.